Elegant Properties wishes to introduce our latest development, TREE TOPS Forest Apartments, an upscale residential project on Peponi Road directly overlooking Karura Forest.
With its proximity to Westlands, its quiet surrounding, and exceptional Forest front setting, the Tree Tops location is beyond compare to any other apartment residence in Nairobi.
The development consists of spacious 2, 3 and 4 bedroom apartments, finished to the highest standards. The forest-facing 3 and 4 bedroom apartments are especially spectacular, with unobstructed views of the Karura forest vista.
4 bedroom units feature a unique, indoor and outdoor shower attached to the master bedroom, the floor spaces are very large, with large floor to ceiling windows to take advantage of the dazzling forest views.
Property Features
Location Map
Floor Plans
Construction Updates
April 2021 - Tree Tops is complete!






March 2021 - Tree Tops is complete!






July 2020 - Construction Update









October 2018 - Construction Update
6th slab completed at river level, 4th slab completed in middle section, basements at road level under progress, show house projected for March 2019



August 2018 - Construction Update
5th slab at river level and 4th slab in middle section under progress



May 2018 - Construction Update
Foundations complete, 3rd floor at river level under progress and almost completed




March 2018 - Construction Update
First floor at river level, casting in progress



April 2019 - Construction Update
9th floor slab in progress